Twenty workers can finish a piece of work in 30 days. After how many days should 5 workers leave the job to complete the work in 35 days?
Ashutosh Nautiyal
October 01, 2021
Twenty workers can finish a piece of work in 30 days. After how many days should 5 workers leave the job to complete the work in 35 days?
A. 5 days
B. 10 days
C. 15 days
D. 20 days
Show Answer
The correct answer is option
C. 15 days
. Can you explain this answer in the comments?
View Complete Solution Here
Books I recommend for Quantitative Aptitude:
1. How to Prepare for Quantitative Aptitude for CAT by Arun Sharma
2. Ace Quantitative Aptitude For Banking and Insurance
3. Quantitative Aptitude Quantum CAT by Sarvesh K Verma
4. Quantitative Aptitude for Competitive Examinations by R.S. Aggarwal
5. Best 4000 Smart Practice Questions for Banking by S. Chand Experts
0 Comments
Newer
Older
Popular Posts
A Re-assurance sign is a
November 15, 2021
Errors in Measurements | Introduction to Surveying | Explanatory Video | By Ashutosh Nautiyal
September 15, 2020
How to draw lines using Absolute Coordinate System in AutoCAD | Coordinate System | AutoCAD Tutorials | By Akhand Dutta
July 03, 2020
Articles
3/Article/post-list
Recommended For You
Contact form
0 Comments