Twenty workers can finish a piece of work in 30 days. After how many days should 5 workers leave the job to complete the work in 35 days?


Twenty workers can finish a piece of work in 30 days. After how many days should 5 workers leave the job to complete the work in 35 days?

  • A. 5 days
  • B. 10 days
  • C. 15 days
  • D. 20 days
 

The correct answer is option C. 15 days. Can you explain this answer in the comments?


View Complete Solution Here