Chapter - Time and Work
Difficulty Level of Questions - 1 (Out of 3)
Q.1. 6 men can do a piece of work in 12 days. How many men are needed to do the work in 18 days?
A. 3 men
B. 6 men
C. 4 men
D. 2 men
Solution:-
Q.2. Baba alone can do a piece of work in 10 days. Anshu alone can do it in 15 days. If the total wages for the work is ₹ 50. How much should Baba be paid if they work together for the entire duration of the work?
A. ₹ 30
B. ₹ 20
C. ₹ 50
D. ₹ 40
Solution:-
Q.3. 4 men and 3 women finish a job in 6 days, and 5 men and 7 women can do the same job in 4 days. How long will 1 man and 1 woman take to do the work?
A. 22 [2/7] days
B. 25 [1/2] days
C. 5 [1/7] days
D. 12 [7/22] days
Solution:-
Q. 4. A can do a piece of work in 10 days and B can do the same work in 20 days. With the help of C, they finish the work in 5 days. How long will it take for C alone to finish the work?
A. 15 days
B. 10 days
C. 35 days
D. 20 days
Solution:-
Q. 5. A can do a piece of work in 20 days. He works at it for 5 days and then B finishes it in 10 more days. In how many days will A and B together finish the work?
A. 8 days
B. 10 days
C. 12 days
D. 6 days
Solution:-
Q.6. Twenty workers can finish a piece of work in 30 days. After how many days should 5 workers leave the job to complete the work in 35 days?
A. 5 days
B. 10 days
C. 15 days
D. 20 days
Solution:-
Q.7. Arun and Vinay together can do a piece of work in 7 days. If Arun does twice as much work as Vinay in a given time, how long will Arun alone take to do the work?
A. 6.33 days
B. 10.5 days
C. 11 days
D. 72 days
Solution:-
Q.8. Subhash can copy 50 pages in 10 hours; Subhash and Prakash together can copy 300 pages in 40 hours. In how much time can Prakash copy 30 pages?
A. 13 h
B. 12 h
C. 11 h
D. 9 h
Solution:-
Q.9. Raju can do a piece of work in 10 days, Vicky in 12 days and Tinku in 15 days. They all start the work together, but Raju leaves after 2 days and Vicky leaves 3 days before the work is completed. In how many days is the work completed?
A. 5 days
B. 6 days
C. 7 days
D. 8 days
Solution:-
Q.10. X number of men can finish a piece of work in 30 days. If there were 6 men more, the work could be finished in 10 days less. What is the original number of men?
A. 10
B. 11
C. 12
D. 15
Solution:-
Questions Courtesy: How to prepare for Quantitative Aptitude for CAT by Arun Sharma
Books I recommend for Quantitative Aptitude:
1. How to Prepare for Quantitative Aptitude for CAT by Arun Sharma
2. Ace Quantitative Aptitude For Banking and Insurance
3. Quantitative Aptitude Quantum CAT by Sarvesh K Verma
4. Quantitative Aptitude for Competitive Examinations by R.S. Aggarwal
*Self Typed
*Source- Books, Internet, Self-Analysis