Which method is used to determine the most cost-effective design and construction procedure?
Ashutosh Nautiyal
November 08, 2021
Which method is used to determine the most cost-effective design and construction procedure?
A. Life cycle cost analysis
B. Cost-benefit analysis
C. Inductive economic analysis
D. Deductive economic analysis
Show Answer
The correct answer is option
A. Life cycle cost analysis
. Can you explain this answer in the comments?
Book For Transportation Engineering MCQs and Solved Question -
CLICK TO VIEW
0 Comments
Newer
Older
Popular Posts
Calculate the probability of an electron occupying an energy level 0.02 eV above the Fermi level at 200 K and 400 K in a material.
May 17, 2020
Find the temperature at which there is 1.0 % probability that a state with energy 0.5 eV above Fermi energy will be occupied.
May 17, 2020
Which of the following equations is correct for the Pozzolanic reaction? (A) Ca(OH)2 + Reactive Superplasticiser + H2O = C-S-H (B) Ca(OH)2 + Reactive Silicon dioxide + H2O = C-S-H (C) Ca(OH)2 + Reactive Sulphates + H2O = C-S-H (D) Ca(OH)2 + Reactive Sulphur + H2O = C-S-H | GATE 2022
June 28, 2023
Articles
3/Article/post-list
Recommended
Contact form
0 Comments